新人求问CMII中成本问题!!!

Cost of documentation ($200,000.) plus cost of producing the physical items ($100,000.)would total $300,000., if 100% conformance is achieved during the 1st build cycle
1.What is the extra cost of upgrading documentation?
2.What is the extra cost of rework and/or replacement of physical items?
3.What is the total cost of the 1st unit including all rework and all upgrades?
4.What would the "planned cost" be to build a 2nd identical unit if the
documentation from the 1st cycle is upgraded and used as the starting point?
5.What will the actual cost of the 2nd unit be if rework/replacement and document correction costs are the same as experienced with the 1st unit?